Planned Somerset nuclear plant on hold ? or not ?

Is nuclear fission going to make a comeback and plug the gap in our energy needs? Will nuclear fusion ever become energetically viable?

Moderator: Peak Moderation

Pepperman
Posts: 772
Joined: 10 Oct 2010, 09:00

Post by Pepperman »

Britain’s nuclear strategy exposed at Hinkley Point

Ten years ago, when the British government first considered launching a new nuclear programme, Areva, the French nuclear technology company, said it could build reactors that would produce electricity profitably at £24 per megawatt-hour.

It seemed an attractive proposition. Not only was this less than previous reactors, it was competitive with other power sources. New technology seemed to have opened the door to affordable carbonless electricity; Britain could meet its ever-tougher climate goals without shaking the public down.

A decade on and a major nuclear accident later, the world knows better. Nuclear projects elsewhere have been scrapped and existing stations shuttered or scheduled for early closure. Meanwhile stringent regulations have exposed Areva’s promise as a chimera. It turns out that the price of new nuclear for Britain is not £24 per MWh but nearly four times as much.
Even at these elevated prices, Britain’s first proposed new station, at Hinkley Point, is in difficulty. Despite agreeing a deal in 2013, EDF, the developer, has yet to commit to the £18bn project. There are concerns about technology and the French group’s financial capacity. Hinkley Point C — if it opens — may be materially delayed.

The government has done its best to make things easy. It eschewed a competitive bidding process and guaranteed to buy electricity from Hinkley Point at a £92.50 per MWh index-linked for 35 years after the station has been commissioned.

That is no small commitment. Few would bet on wholesale energy prices holding steady at more than double their present level for the next three and a half decades. Indeed some expect them to fall. The idea, though, was to get the station built fast, kick-start other nuclear projects and, critically, underpin the government’s self-imposed intention to cut carbon emissions by an EU-beating 60 per cent by 2030.

The French face several obstacles. First, there is the question of EDF’s balance sheet, groaning under a €37bn debt pile. The company’s share price has more than halved in the past year and its market capitalisation is now about €21bn. That is not much more than the company’s 67 per cent share of the cost of Hinkley C.

Linked to this are worries about the reactor technology it is employing. The two projects under construction, including EDF’s at Flamanville in France, are delayed and over budget. It might be difficult to entice lenders while it is possible that problems with Flamanville might cause construction to be halted or scrapped.

Politicians have come this far down the road with Hinkley Point because of the constraints they are under. Despite life-extensions, the UK’s existing nuclear stations are near to closing and its dirtiest coal plants are being shut to comply with EU rules. New capacity is needed. Replacing coal with gas would reduce carbon emissions but not enough to meet the targets the government has set itself.

New nuclear might not be needed were the UK to rethink its costly promises and reduce its carbon targets to match those of other EU states. If new reactors are to be considered, however, they must be subjected to the rigours of competition. That is the only way to get the right technology at acceptable cost.

Britain is saddled with the worst of all worlds. The government has effectively written the French a long-dated option to sell it unproven technology at an extremely generous price. Politically painful it may be, but the case for halting Hinkley Point C is becoming hard to refute.
I was trying to gather cost estimates from back when new nuclear was put back on the table but hadn't come across the £24/MWh figure. It truly was a disgraceful bait and switch and the government fell for it hook, line and sinker.

http://www.ft.com/cms/s/0/9d484f08-d63c ... 28e54.html

Or if the FT's paywall stops you, google the headline and you can get in that way.
User avatar
biffvernon
Posts: 18538
Joined: 24 Nov 2005, 11:09
Location: Lincolnshire
Contact:

Post by biffvernon »

Nice one. 10 years ago, just as people were becoming aware of peak oil and energy prices looked as though they might rise a lot, £24/MWh must have looked tempting.
User avatar
adam2
Site Admin
Posts: 10926
Joined: 02 Jul 2007, 17:49
Location: North Somerset, twinned with Atlantis

Post by adam2 »

This was reported on during tonight's evening TV news.
The main focus of the report was that the French trade unions that represent the EDF staff are strongly opposed to Hinckley C.

The unions want the project paused for up to 3 years whilst it is re-evaluated for value for money.

It is uncommon for trades unions to be opposed to this sort of project, they normally welcome the extra work provided and the potential for more members.
In this case I suspect that the unions fear it will bankrupt EDF and thereby endanger existing jobs and pensions.
"Installers and owners of emergency diesels must assume that they will have to run for a week or more"
User avatar
biffvernon
Posts: 18538
Joined: 24 Nov 2005, 11:09
Location: Lincolnshire
Contact:

Post by biffvernon »

Molly Scott Cato is (quite rightly) convinced that Hinkley C will never be built.
http://leftfootforward.org/2016/03/comm ... s-volumes/
User avatar
biffvernon
Posts: 18538
Joined: 24 Nov 2005, 11:09
Location: Lincolnshire
Contact:

Post by biffvernon »

EDF Chief Financial Officer Thomas Piquemal resigned over #HinkleyC http://www.bloomberg.com/news/articles/ ... sagreement
User avatar
alex
Posts: 61
Joined: 24 May 2010, 15:44
Location: Cannington Somerset
Contact:

Post by alex »

Another one jumps ship.

It is all down to money, so they say; but perhaps lack of confidence in the whole affair compounded with safety and composition flaws in the nuclear flasks as constructed by the almost defunct company Areva which the state owned Électricité de France has recently inherited.

Away from its financial health, EDF has some pressing and expensive operational matters at home. Especially regarding life extension of its 58 reactors in France estimated to cost about €55bn. That doesn’t bode well either, the cost therefore will be significantly greater to EDF than the HPC build and causing them to be walking away thus abandoning the site and concentrate on issues at home.

The proposed plant for HPC is an EPR. There isn’t a single nuclear plant of this type working anywhere. The three sites where EPRs are under construction are all in serious difficulty. The Flamanville EPR in France is facing huge problems with its metallurgical flaws in the reactor vessel and lid and it's odds on that it will never be completed due to the massively escalating costs, delays, and safety concerns.

Additionally there are questions over the Olkiluoto EPR in Finland, as the costs of completion are now grossly over-time and are coupled with this flawed reactor which appears may need to be replaced even before commissioning.

Most likely to be completed is the twin-reactor Taishan EPR in China, which was meant to come in last of the bunch but is now well ahead. However there are widespread suspicions that the reactors, again supplied by Areva which may suffer from the same flaws as those at Flamanville and Olkiluoto. Strangely the Chinese aren't giving out much information.

Even if the Chinese plant is built to completion, Chinese safety regulators may never allow it to be turned on due to the above issues with the vessel.

What gets me is should they pull out, it will be like the cat that crept in the crypt, and crept out again. Leaving us with roads and junctions that have been tinkered with, a by-pass around the village of Cannington that nobody uses, and a lot of business owners who will be totally bewildered as to what went wrong; moreover where do they stand now?

I feel for local businesses, although a lot of the procurement will not be local, there have been schemes and other initiatives promised for this area that may well evaporate. Therefore those who have restructured their business, submitted new business plans and invested ready for the project could be left in a parlous state.

One that will sadden me if the whole concept is abandoned will be the loss of opportunity, not only for local business, not only for the knock-on-effect and growth in the area, but the fact a lot of young people would have lost the prospect of excellent training with skill sets for the future. They would have built the legacy and become part of the prosperous community for several generations.

We could have done the job ourselves, and probably made it work.
If it wasn't for pick-pockets & frisking at airports, I'd have no sex life at all .................Rodney Dangerfield.
User avatar
biffvernon
Posts: 18538
Joined: 24 Nov 2005, 11:09
Location: Lincolnshire
Contact:

Post by biffvernon »

The life of the some of the UK fleet is being extended but we haven't heard much about whether there will be costs involved. Anyone know?
User avatar
adam2
Site Admin
Posts: 10926
Joined: 02 Jul 2007, 17:49
Location: North Somerset, twinned with Atlantis

Post by adam2 »

"will go ahead, according to EDF"

They seem confidant, but of course we have heard numerous broadly similar statements in the past.

http://www.bbc.co.uk/news/business-35790824

EDF are reluctant to fully fund their share of the project, but seem to be presuming that the French government will pay the rest.
"Installers and owners of emergency diesels must assume that they will have to run for a week or more"
User avatar
biffvernon
Posts: 18538
Joined: 24 Nov 2005, 11:09
Location: Lincolnshire
Contact:

Post by biffvernon »

Pots can be half full or half empty.

EDF chief executive Jean-Bernard Levy said they will not go ahead with its plan to build Hinkley C unless it gets more financial support from the French state.

That makes it crystal clear that it is not commercially viable but can only go ahead with a political decision (which is going to hit the EU competition and subsidy buffers).
User avatar
adam2
Site Admin
Posts: 10926
Joined: 02 Jul 2007, 17:49
Location: North Somerset, twinned with Atlantis

Post by adam2 »

Already looking less certain than was implied less than 24 hours ago.

http://www.bbc.co.uk/news/business-35793445
"Installers and owners of emergency diesels must assume that they will have to run for a week or more"
User avatar
clv101
Site Admin
Posts: 10569
Joined: 24 Nov 2005, 11:09
Contact:

Post by clv101 »

biffvernon wrote:The life of the some of the UK fleet is being extended but we haven't heard much about whether there will be costs involved. Anyone know?
Costs? It's cheaper to extend compared to start decommissioning. Decommissioning is when it gets expensive and you lose the revenue stream.
User avatar
biffvernon
Posts: 18538
Joined: 24 Nov 2005, 11:09
Location: Lincolnshire
Contact:

Post by biffvernon »

Ha! Good point. But there are still costs and we haven't heard much about them.
User avatar
adam2
Site Admin
Posts: 10926
Joined: 02 Jul 2007, 17:49
Location: North Somerset, twinned with Atlantis

Post by adam2 »

According to tonight's evening news, Hinckley C "definitely going ahead" and a also a(nother) final decision will be made in May.

There seems to be a mismatch between the definitely going ahead bit, and the final decision in a couple of months bit.
"Installers and owners of emergency diesels must assume that they will have to run for a week or more"
User avatar
PS_RalphW
Posts: 6974
Joined: 24 Nov 2005, 11:09
Location: Cambridge

Post by PS_RalphW »

French unions calling for another 2 year delay for another redesign.

http://www.theguardian.com/business/201 ... uest-delay
Post Reply