Page 2 of 2

Posted: Thu Feb 06, 2020 10:04 pm
by adam2
Latest delays.
Reactor 3 that was due to re-start on Feb 28, is now not forecast to start until April 10, another 6 weeks delay.

Reactor 4 that was due to re-start on March 13, is now not forecast to start until April 24, also about 6 weeks late.

Posted: Thu Feb 06, 2020 11:51 pm
by clv101
Feel sorry for the poor sod who's job it is manage this project... or I wonder how many project managers they've got through in the last year!?

Feel like they could have saved a lot of work/cost by just starting the decommission last year - what's the best case, a few more years at 2/3 power? Hardly seems worth it.

Posted: Fri Feb 07, 2020 5:24 am
by BritDownUnder
clv101 wrote:Feel sorry for the poor sod who's job it is manage this project... or I wonder how many project managers they've got through in the last year!?

Feel like they could have saved a lot of work/cost by just starting the decommission last year - what's the best case, a few more years at 2/3 power? Hardly seems worth it.
I can think of a few project managers who would like this. on their last job before retirement they can make a bit more 'beer money'. One I knew hung on so he would get a good redundancy package.

It does look like this reactor is toast. The UK could be in a bad way once all of the AGRs have closed unless some reliable and firm generation can be came up with.

Posted: Thu Apr 02, 2020 1:07 pm
by adam2
Latest delays at Hunterston.

Reactor 3 that was due to re-start on April 10 is now forecast to re-start on June first.
Reactor 4 that was due to re-start on April 24 is now forecast to re-start on June 15.

Posted: Thu Apr 02, 2020 2:20 pm
by kenneal - lagger
Is this what you call "rolling maintenance?"

Posted: Tue Jun 02, 2020 3:35 pm
by adam2
Latest delays.
Reactor 3 that was due to restart on June 1st is now forecast to start on July 13.
Reactor 4 that was due to restart on June 15 is now forecast to restart on July 27.

About the usual 6 week delay.

Of little near term concern as demand is reduced by coronavirus, and indeed another reactor is shutdown at the request of the national grid due to low demand.

Potentially concerning in the longer term as the two reactors in question represent about 2% of peak demand.

Posted: Fri Jul 10, 2020 10:24 am
by adam2
Latest delays.
Reactor three that was due to restart on July 13 is now expected to start on august 20.

Reactor 4 that was due to restart on July 27 is now expected to start on September 17.

Posted: Fri Jul 10, 2020 10:47 am
by BritDownUnder
There seems to be a trend here.

Posted: Sun Jul 19, 2020 10:59 pm
by clv101
This thing needs to be put out of its misery, UK power demand is likely to be depressed for at least a year.

Posted: Sat Aug 08, 2020 1:39 am
by adam2
latest delay is much smaller than previous delays.
The reactor that was due to start August 20, is now forecast to start August 30, a delay of only 10 days rather than the previous delays of several weeks.
The other reactor is still forecast to start September 17.

Posted: Wed Sep 02, 2020 2:29 pm
by adam2
clv101 wrote:This thing needs to be put out of its misery, UK power demand is likely to be depressed for at least a year.
Now due to be "put out of its misery" final shutdown of both Hunterston reactors is planned for no latter than beginning of January 2022.
Edited to add, one reactor at Hunterston is now at full load, having presumably re-started a few days ago and then gradually increased load.
Final closure is still reported as being no later than very early in 2022.

Posted: Mon Sep 21, 2020 1:20 am
by adam2
The reactor that was due to restart September 17 is now expected to re-start September 29, a modest delay that suggests that might actually start soon.
The other reactor is running.

Posted: Tue Sep 29, 2020 6:55 am
by adam2
Both reactors at Hunterston B are now working, an unusual situation in recent years.